The construction activities of the TRA facility (Temporary Relocation Area) is progressing well. The civil contractor (Entsha Henra) is finishing up with the civil works (road construction and connection of ablution blocks), while the top structure contractor (Asla Construction) is continuing with the erection of the housing units and storage units. The electrification of the … Continue reading TRA Construction update 18 July 2022
Entsha Henra
TRA Construction Update – 13 June 2022
The first of the 250 TRA units are being erected and the construction of the retaining walls are progressing well:
Call for Subcontractors – Advert 2
PRE-QUALIFICATION OF SUB CONTRACTORS FOR CONSTRUCTION OF A PORTION CIVIL ENGINEERING SERVICES FOR 680 ERVEN AND TEMPORARY RELOCATION AREA (TRA): PHASE 2 You are hereby invited to submit a pre-qualification application for sub-contracting appointment of level CIDB 3 CE and 4 CE for sub-contracting work on a portion of the services for 680 erven in … Continue reading Call for Subcontractors – Advert 2
Call for local Subcontractors
Mossel Bay Thusong e-Centre PRE-QUALIFICATION OF SUB CONTRACTORS FOR CONSTRUCTION OF A PORTION CIVIL ENGINEERING SERVICES FOR 680 ERVEN AND TEMPORARY RELOCATION AREA (TRA): PHASE 2 You are hereby invited to submit a pre-qualification application for sub-contracting appointment of level CIDB 3 GB and 4 GB for sub-contracting work on a portion of the services … Continue reading Call for local Subcontractors
Construction update at TRA Facility – 8 June 2022
The construction activities for the first phase of the Mossel Bay UISP is progressing well. The civil contractor (Entsha Henra) started with construction of the retaining walls at the TRA facility (Temporary Relocation Area). The TRA will consist of 250 housing units together with ablution facilities and storage and will temporarily accommodate the households that … Continue reading Construction update at TRA Facility – 8 June 2022
TRA Facility Construction update 1 June 2022
The construction work at the Temporary Relocation Area (TRA) is progressing well. The groundwork for the platforms have mostly been completed and work on the retaining walls and the internal infrastructure has started. See a slideshow of the latest photos below and visit this site regularly for more updates.
Construction Progress 18 May 2022
The Contractor, Entsha Henra (Pty) Ltd is currently busy with the construction of the services for the Temporary Relocation Area (TRA) and the delivery of the first containerised ablutions facilities has taken place on site. Construction has also started in the Transand Camp Informal Settlement area. See the photos below illustrating the latest progress: Contractor's … Continue reading Construction Progress 18 May 2022
First Ablution Blocks are being delivered to the TRA site
TRA Facility Construction Progress
Construction is progressing well at the TRA facility. The civil contractor (Entsha-Henra) is preparing the site by building platforms, making the access road, and installing the ablution blocks and water and sewer infrastructure required to accommodate the 250 TRA units that will be erected on the site.
Mossel Bay UISP Phase 1 construction update
The construction activities for the first phase of the UISP is now truly underway. The civil contractor (Entsha Henra) started with construction at the TRA facility and have already cleared the site and started with earth works. The TRA facility (Temporary Relocation Area) will consist of 250 housing units together with ablution facilities and storage … Continue reading Mossel Bay UISP Phase 1 construction update
Sourcing of Local Labour for Construction Activities in Phase 1 of the Mossel Bay UISP
The sourcing of local general labourers in Mossel Bay that can assist the contractor with construction activities of the first phase of the Mossel Bay UISP is handled by way of a “shake-shake” process. The Strategic Service Department at the Mossel Bay Municipal is responsible to arrange the process called Shake-shake to employ local labourers. … Continue reading Sourcing of Local Labour for Construction Activities in Phase 1 of the Mossel Bay UISP
Mossel Bay UISP – Informal Settlement Forum Meeting 5 April 2022
An Informal Settlement Forum Meeting was held on 5 April 2022. All the BLCs of the informal settlement areas in KwanonQaba were invited. The meeting was well represented by the members of most of the areas as well as Ward Councillors, Municipal Officials, the Implementing Agent (Zutari) as well as the contractor for phase 1 … Continue reading Mossel Bay UISP – Informal Settlement Forum Meeting 5 April 2022
Update – Interim Shared Basic Services – Final handovers
The construction of the interim shared basic services is the first step in the incremental upgrading process of the UISP and reached a major milestone in the last week. The final handovers of infrastructure (toilets and taps) were completed in the following areas: Asla Park A, B C & DSewendelaanEmfuleniTransand CampPA CampGentswana A, B & … Continue reading Update – Interim Shared Basic Services – Final handovers
Construction Update – IBS
The construction activities of the installation of the interim basic services (IBS) are progressing well. The contractor Entsha Henra (Pty) Ltd is appointed to install the shared interim basic services (IBS) to all of the 23 informal settlement areas that form part of the Mossel Bay UISP Project. The site camp was established near the … Continue reading Construction Update – IBS
Contractor for IBS formally appointed!
The contractor Entsha Henra (Pty) Ltd was formally appointed by the Mossel Bay Municipality on Friday 5 April 2019, as the contractors that will install the shared interim basic services (IBS) to all of the 23 informal settlement areas that form part of the Mossel Bay UISP Project! The employer’s agent is currently busy drafting … Continue reading Contractor for IBS formally appointed!