A coordinated attack on the Mossel Bay UISP project erupted in the early hours of Tuesday 23 August 2022. Protestors entered the UISP construction area at Transand Camp and demolished approximately 20 of the 25 completed toilet structures that were built as part of the construction of enhanced serviced sites. Some of the installed water … Continue reading Protest Action disrupts Mossel Bay – UISP Project Destroyed
UISP
Mossel Bay UISP Community Meeting 21 July 2022
The Department of Human Settlements representative Mr. David Alli (Pr Pln) of the Informal Settlement Support Unit from Cape Town attended a UISP meeting with the Phase 1 Transand and Emfuleni (including Growing Hope) communities on Thursday 21st July evening at 18:00. Prior to the meeting, Mr Alli and Zutari visited the temporary relocation area … Continue reading Mossel Bay UISP Community Meeting 21 July 2022
TRA Construction update 18 July 2022
The construction activities of the TRA facility (Temporary Relocation Area) is progressing well. The civil contractor (Entsha Henra) is finishing up with the civil works (road construction and connection of ablution blocks), while the top structure contractor (Asla Construction) is continuing with the erection of the housing units and storage units. The electrification of the … Continue reading TRA Construction update 18 July 2022
TRA Construction Update – 13 June 2022
The first of the 250 TRA units are being erected and the construction of the retaining walls are progressing well:
Call for Subcontractors – Advert 2
PRE-QUALIFICATION OF SUB CONTRACTORS FOR CONSTRUCTION OF A PORTION CIVIL ENGINEERING SERVICES FOR 680 ERVEN AND TEMPORARY RELOCATION AREA (TRA): PHASE 2 You are hereby invited to submit a pre-qualification application for sub-contracting appointment of level CIDB 3 CE and 4 CE for sub-contracting work on a portion of the services for 680 erven in … Continue reading Call for Subcontractors – Advert 2
Call for local Subcontractors
Mossel Bay Thusong e-Centre PRE-QUALIFICATION OF SUB CONTRACTORS FOR CONSTRUCTION OF A PORTION CIVIL ENGINEERING SERVICES FOR 680 ERVEN AND TEMPORARY RELOCATION AREA (TRA): PHASE 2 You are hereby invited to submit a pre-qualification application for sub-contracting appointment of level CIDB 3 GB and 4 GB for sub-contracting work on a portion of the services … Continue reading Call for local Subcontractors
Construction update at TRA Facility – 8 June 2022
The construction activities for the first phase of the Mossel Bay UISP is progressing well. The civil contractor (Entsha Henra) started with construction of the retaining walls at the TRA facility (Temporary Relocation Area). The TRA will consist of 250 housing units together with ablution facilities and storage and will temporarily accommodate the households that … Continue reading Construction update at TRA Facility – 8 June 2022
Inaugural Meeting with Asla Construction for the construction of the TRA units
TDR126/2020/2021: SUPPLY, MANUFACTURE AND INSTALLATION OF PREFABRICATED HOUSING UNITS FOR THE TEMPORARY RELOCATION AREA The Inaugural Meeting with Asla Construction who is the appointed contractor that will construct the 250 TRA housing units, storage units and meeting facility took place on Wednesday 01 June 2022 on the TRA site at Kwanonqaba. Following the preparation of … Continue reading Inaugural Meeting with Asla Construction for the construction of the TRA units
TRA Facility Construction update 1 June 2022
The construction work at the Temporary Relocation Area (TRA) is progressing well. The groundwork for the platforms have mostly been completed and work on the retaining walls and the internal infrastructure has started. See a slideshow of the latest photos below and visit this site regularly for more updates.
Construction Progress 18 May 2022
The Contractor, Entsha Henra (Pty) Ltd is currently busy with the construction of the services for the Temporary Relocation Area (TRA) and the delivery of the first containerised ablutions facilities has taken place on site. Construction has also started in the Transand Camp Informal Settlement area. See the photos below illustrating the latest progress: Contractor's … Continue reading Construction Progress 18 May 2022
Mossel Bay UISP Phase 1 construction update
The construction activities for the first phase of the UISP is now truly underway. The civil contractor (Entsha Henra) started with construction at the TRA facility and have already cleared the site and started with earth works. The TRA facility (Temporary Relocation Area) will consist of 250 housing units together with ablution facilities and storage … Continue reading Mossel Bay UISP Phase 1 construction update
Sourcing of Local Labour for Construction Activities in Phase 1 of the Mossel Bay UISP
The sourcing of local general labourers in Mossel Bay that can assist the contractor with construction activities of the first phase of the Mossel Bay UISP is handled by way of a “shake-shake” process. The Strategic Service Department at the Mossel Bay Municipal is responsible to arrange the process called Shake-shake to employ local labourers. … Continue reading Sourcing of Local Labour for Construction Activities in Phase 1 of the Mossel Bay UISP
Mossel Bay UISP – Informal Settlement Forum Meeting 5 April 2022
An Informal Settlement Forum Meeting was held on 5 April 2022. All the BLCs of the informal settlement areas in KwanonQaba were invited. The meeting was well represented by the members of most of the areas as well as Ward Councillors, Municipal Officials, the Implementing Agent (Zutari) as well as the contractor for phase 1 … Continue reading Mossel Bay UISP – Informal Settlement Forum Meeting 5 April 2022