Winner – 2021 IMESA/CESA EXCELLENCE AWARDS

The Mossel Bay UISP – Emergency Shared Basic Services received the award for the best Community upliftment and job creation project at the biennial IMESA/CESA excellence awards. The IMESA/CESA excellence awards are intended to recognise outstanding achievements in municipal infrastructure. Mr Carel Venter - Director:  Planning & Economic Development, Mossel Bay Municipality and Mr Lindilizwi … Continue reading Winner – 2021 IMESA/CESA EXCELLENCE AWARDS

Community Work Programme providing jobs

In parallel to and integrated with the UISP implementation the WCDoHS has, through its Informal Settlement Support Programme, assigned various NGO’s to municipalities to further assist/enhance the UISP intervention programmes. As part of this initiative, DAG (Development Action Group) has been assigned to Mossel Bay. Part of what this NGO is facilitating and endeavouring to … Continue reading Community Work Programme providing jobs

Update – Interim Shared Basic Services – Final handovers

The construction of the interim shared basic services is the first step in the incremental upgrading process of the UISP and reached a major milestone in the last week. The final handovers of infrastructure (toilets and taps) were completed in the following areas: Asla Park A, B C & DSewendelaanEmfuleniTransand CampPA CampGentswana A, B & … Continue reading Update – Interim Shared Basic Services – Final handovers

IBS Construction update – First infrastructure handed over!

The construction activities as part of the shared interim basic services (IBS) installation to all of the 23 informal settlement areas that form part of the Mossel Bay UISP Project, reached a huge milestone today! The first infrastructure that have been constructed at Brandwacht was handed over to the Mossel Bay Municipality on Thursday 25 … Continue reading IBS Construction update – First infrastructure handed over!

The Contractor gearing up to commence with construction

The contractor Entsha Henra (Pty) Ltd is appointed to install the shared interim basic services (IBS) to all of the 23 informal settlement areas that form part of the Mossel Bay UISP Project. The construction commencement date according to the contract is 30 May 2019 and the construction period will be over a 41 week … Continue reading The Contractor gearing up to commence with construction