Update – Interim Shared Basic Services – Final handovers

The construction of the interim shared basic services is the first step in the incremental upgrading process of the UISP and reached a major milestone in the last week. The final handovers of infrastructure (toilets and taps) were completed in the following areas: Asla Park A, B C & DSewendelaanEmfuleniTransand CampPA CampGentswana A, B & … Continue reading Update – Interim Shared Basic Services – Final handovers

The Contractor gearing up to commence with construction

The contractor Entsha Henra (Pty) Ltd is appointed to install the shared interim basic services (IBS) to all of the 23 informal settlement areas that form part of the Mossel Bay UISP Project. The construction commencement date according to the contract is 30 May 2019 and the construction period will be over a 41 week … Continue reading The Contractor gearing up to commence with construction